Linden 345 kV

PJM queue ID C01-1495

Queue IDC01-1495
Project nameLinden 345 kV
Status (as published)Active
SubstationLinden
Point of interconnectionLinden 345 kV
CountyUnion
StateNJ
Voltage345 kV
Capacity750 MW
Resource (as published)Natural Gas
Resource categoryGas (normalised for filtering)
Target commercial operation2031-04-15
Source datasetcycle

Additional filed fields

DeveloperParkway Generation Operating, LLC
Transmission OwnerPSEG
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy750.0
Mw Capacity750.0
Mfo750.0
Submitted Date4/27/2026
Last Updated6/24/2026