Tosco #6 (Y1-026) is listed in the PJM interconnection queue as a 160 MW gas project in Union County, NJ. The filing names Tosco as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of March 1, 2012.

Queue IDY1-026
Project nameTosco #6
Status (as published)In Service
SubstationTosco
Point of interconnectionTosco 230kV
CountyUnion
StateNJ
Voltage230 kV
Capacity160 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2012-03-01
Source datasetserial

Same substation and county

Tosco substation: 2 requests in the PJM queue, 2 active totaling 180 MW.

Queue IDProjectMWResourceStatus
S61Tosco #620GasIn Service

Union, NJ: 40 requests in the PJM queue, 21 active totaling 3,558.8 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy0
MW capacity160
MFO180

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.