Rock Island, IL interconnection queue

6 active projects totalling 331 MW in the PJM queue, plus 2 with terminal status (shown greyed).

6active projects
331active MW
8total filed
Queue IDProjectkVMWResourceStatus
Q51 Quad Cities - Units 1 & 2 345 140 Nuclear In Service
C01-1586 Cordova 345 kV 345 80 Battery Active
AG2-517 Cordova Energy Center 345kV 345 72 Hybrid Withdrawn
C01-1584 Cordova 345 kV 345 48 Battery Active
AG2-675 Cordova 345 kV 345 32 Battery Active
X3-046 Quad Cities n/r 32 Nuclear Withdrawn
C01-1054 Quad City 345 kV 345 31 Nuclear Active
AG1-553 Beacon Solar 345 0 Solar EP

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.