Quad City 345 kV
PJM queue ID C01-1054
Quad City 345 kV (C01-1054) is listed in the PJM interconnection queue as a 31 MW nuclear project in Rock Island County, IL. The filing names Quad City as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of March 29, 2028.
| Queue ID | C01-1054 |
|---|---|
| Project name | Quad City 345 kV |
| Status (as published) | Active |
| Substation | Quad City |
| Point of interconnection | Quad City 345 kV |
| County | Rock Island |
| State | IL |
| Voltage | 345 kV |
| Capacity | 31 MW |
| Resource (as published) | Nuclear |
| Resource category | Nuclear (normalized for filtering) |
| Target commercial operation | 2028-03-29 |
| Source dataset | cycle |
Same substation and county
Quad City substation: 2 requests in the PJM queue, 2 active totaling 171 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| Q51 | Quad Cities - Units 1 & 2 | 140 | Nuclear | In Service |
Rock Island, IL: 8 requests in the PJM queue, 5 active totaling 283 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Constellation Energy Generation, LLC |
|---|---|
| Transmission owner | ComEd |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 31.0 |
| MW capacity | 31.0 |
| MFO | 1945.0 |
| Submitted date | 4/24/2026 |
| Last updated | 5/29/2026 |