Pulaski Solar (AF2-106) is listed in the PJM interconnection queue as a 90 MW solar project in Pulaski County, VA. The filing names Hazel Hollow-Glen Lyn #1 as its point of interconnection. PJM lists its status as “Engineering and Procurement”, with a target commercial operation date of February 28, 2029.

Queue IDAF2-106
Project namePulaski Solar
Status (as published)Engineering and Procurement
SubstationHazel Hollow-Glen Lyn #1
Point of interconnectionHazel Hollow-Glen Lyn #1 138 kV
CountyPulaski
StateVA
Voltage138 kV
Capacity90 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2029-02-28
Source datasetserial

Same substation and county

Pulaski, VA: 27 requests in the PJM queue, 4 active totaling 152.1 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy150
MW capacity90
MFO150

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first