Gutenberg Solar
PJM queue ID AA2-174
Gutenberg Solar (AA2-174) is listed in the PJM interconnection queue as a 2.4 MW solar project in Northhampton County, NC. The filing names Carolina-Jackson as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of April 22, 2019.
| Queue ID | AA2-174 |
|---|---|
| Project name | Gutenberg Solar |
| Status (as published) | In Service |
| Substation | Carolina-Jackson |
| Point of interconnection | Carolina-Jackson 115kV |
| County | Northhampton |
| State | NC |
| Voltage | 115 kV |
| Capacity | 2.4 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2019-04-22 |
| Source dataset | serial |
Same substation and county
Carolina-Jackson substation: 2 requests in the PJM queue, 2 active totaling 54.8 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AA2-053 | Gutenberg Solar | 52.4 | Solar | In Service |
Northhampton, NC: 18 requests in the PJM queue, 5 active totaling 313.4 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 5 |
| MW capacity | 2.4 |
| MFO | 79.9 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.