Greenbrier, WV interconnection queue
4 active projects totalling 89.5 MW in the PJM queue, plus 7 with terminal status (shown greyed).
4active projects
89.5active MW
11total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| O45 | University Park | n/r | 143 | Not reported | Withdrawn |
| N09 | West Greenbrier | 138 | 90 | Coal | Withdrawn |
| C01-1230 | Nutall - Quinwood 138 kV | 138 | 45 | Solar | Active |
| N02_AEP139 | McClung 138kV | 138 | 40 | Wind | Withdrawn |
| M24 | Beech Ridge / Field Mtn WF | n/r | 37.2 | Hybrid | In Service |
| AG1-234 | Hinton-Ronceverte 115 kV | 115 | 30 | Solar | Withdrawn |
| AH1-376 | Trillium PV I | 46 | 16.8 | Solar | Withdrawn |
| Q61 | Grassy Falls 138kV | 138 | 10 | Coal | Withdrawn |
| AB1-150 | Beech Ridge Wind Farm | 138 | 6.7 | Wind | In Service |
| AE1-086 | Beech Ridge Wind Farm | 138 | 0.6 | Wind | In Service |
| AC1-012 | Tri-State Solar | 34.5 | 0 | Solar | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.