Queue IDAF1-233
Project nameFleming Solar
Status (as published)EP
SubstationFlemingsburg – Spurlock
Point of interconnectionFlemingsburg – Spurlock 138kV
CountyFleming
StateKY
Voltage138 kV
Capacity113.1 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2029-03-31
Source datasetcycle

Additional filed fields

DeveloperAEUG Fleming Solar, LLC
Transmission OwnerEKPC
Project TypeGeneration Interconnection
CycleTC1
StageFINAL AGREEMENT
Mw Energy188.5
Mw Capacity113.1
Mfo188.5
Submitted Date9/27/2019
Last Updated2/9/2026