Hunterstown CT Facility (AF1-193) is listed in the PJM interconnection queue as a 4 MW gas project in Adams County, PA. The filing names Hunterstown as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of September 30, 2023.

Queue IDAF1-193
Project nameHunterstown CT Facility
Status (as published)In Service
SubstationHunterstown
Point of interconnectionHunterstown 115 kV
CountyAdams
StatePA
Voltage115 kV
Capacity4 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2023-09-30
Source datasetserial

Same substation and county

Hunterstown substation: 9 requests in the PJM queue, 4 active totaling 2,131.9 MW.

Queue IDProjectMWResourceStatus
C01-1881Hunterstown 230 kV931.1GasActive
A36Hunterstown830GasIn Service
C01-1398Hunterstown 500 kV366.8GasActive
AB1-153Hunterstown 500kV985.1GasWithdrawn
A60Hunterstown 500 kV679GasWithdrawn
AE1-139Hunterstown 115 kV39SolarWithdrawn
W4-022Hunterstown 230kV38SolarWithdrawn
W1-075Hunterstown 115kV7.6SolarWithdrawn

Adams, PA: 86 requests in the PJM queue, 13 active totaling 2,270.3 MW.

A substation with the same name is named in PJM transmission planning materials: Hunterstown (METED, 5 mentions).

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy4
MW capacity4
MFO65

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first