Adams, OH interconnection queue

4 active projects totalling 347 MW in the PJM queue, plus 17 with terminal status (shown greyed).

4active projects
347active MW
21total filed
Queue IDProjectkVMWResourceStatus
S12 Killen 345kV 345 1,300 Coal Withdrawn
AH1-758 Not reported n/r 500 Battery Withdrawn
C01-1734 Stuart - Don Marquis 345 kV 345 300 Nuclear Active
AH2-146 Adams - Seaman 69 kV 69 52.3 Hybrid Withdrawn
AD2-053 South Canton-Harmon 345kV 345 50 Not reported Withdrawn
AE1-078 Greendale-Miami Fort 138kV Upgrades 138 50 Not reported Withdrawn
AH2-284 Adams 138 kV 138 49.9 Hybrid Withdrawn
AI2-030 Poplar Flat Switch - Brown Hill 69 kV 69 40 Hybrid Withdrawn
AB2-085 Stone Branch Solar 138 33.9 Solar Withdrawn
AI1-151 Kyger Creek - Pierce 345 kV 345 31.9 Solar Withdrawn
AG1-068 London-Tangy 69 kV 69 30.5 Solar Withdrawn
AB2-103 Seaman 138kV 138 27.2 Solar Withdrawn
P61 Gavin 1 765 20 Coal In Service
P62 Gavin 2 765 20 Coal In Service
AC2-056 Killen 345kV 345 13.4 Solar Withdrawn
U1-090 Killen Electric Generating Station 345 12 Coal Deactivated
P51 Stuart Electric Generating Station 345 7 Coal In Service
AG2-503 Adams 138 kV 138 5 Battery Withdrawn
Y3-081 Not reported n/r 0.1 Gas Withdrawn
AE1-049 Tanners Creek - Miami Fort Upgrade Acceleration (b2828; b2831; b2968) n/r 0 Not reported Withdrawn
AH1-109 Krendale - Unionville 12.47 kV 12.5 0 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.