Queue IDProjectkVMWResourceStatus
J3647 Not reported n/r 220 Battery Withdrawn
G905 Not reported 138 200 Wind Operational
J1065 Not reported 138 200 Wind Withdrawn
J176 Not reported 345 200 Wind Withdrawn
J222 Not reported 345 200 Wind Withdrawn
J3634 Not reported n/r 200 Battery Withdrawn
J533 Not reported 345 200 Wind Operational
J984 Not reported 345 200 Wind Active
J3909 Not reported 138 175 Wind Active
G934 Not reported 345 150 Wind Operational
J589 Not reported 138 148.8 Wind Operational
J132 Not reported 345 125 Wind Operational
J3792 Not reported 138 125 Solar Active
G918 Not reported 138 120 Wind Withdrawn
J199 Not reported n/r 120 Wind Withdrawn
J2026 Not reported n/r 100 Battery Active
J3268 Not reported n/r 100 Battery Active
S1011 Surplus; Polaris Solar 345 100 Hybrid Withdrawn
S1020 Surplus; Polaris Solar 345 100 Hybrid Active
S1021 Surplus; Pine River Solar n/r 80 Hybrid Active
S1010 Surplus; Gratiot Solar 138 50 Hybrid Withdrawn
J749 Not reported 138 20 Battery Withdrawn
J794 Not reported 138 12.5 Wind Operational
J246 Not reported 345 7 Wind Operational
J445 Not reported 345 2 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first