Adair, IA interconnection queue
8 active projects totaling 2,181 MW in the MISO queue, plus 7 with terminal status (shown grayed).
8active projects
2,181active MW
15total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| J355 | Not reported | 345 | 810 | Gas | Withdrawn |
| J500 | Not reported | 345 | 500 | Wind | Operational |
| R52 | Not reported | 345 | 500 | Wind | Withdrawn |
| J364 | Not reported | 345 | 464 | Gas | Withdrawn |
| J499 | Not reported | 345 | 340 | Wind | Operational |
| E0002 | Orient Energy Center | 345 | 265 | Gas | Active |
| J3047 | Not reported | 345 | 263 | Gas | Active |
| J3553 | Not reported | n/r | 263 | Gas | Withdrawn |
| S1111 | Surplus; J500 | n/r | 263 | Hybrid | Active |
| J527 | Not reported | 345 | 250 | Wind | Operational |
| J528 | Not reported | 345 | 200 | Wind | Withdrawn |
| R38 | Not reported | 345 | 200 | Wind | Operational |
| R53 | Not reported | 161 | 200 | Wind | Withdrawn |
| R41 | Not reported | 345 | 100 | Wind | Operational |
| J3554 | Not reported | n/r | 96 | Wind | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.