Substation Scout

Adair, IA interconnection queue

8 active projects totaling 2,181 MW in the MISO queue, plus 7 with terminal status (shown grayed).

8active projects
2,181active MW
15total filed
Queue IDProjectkVMWResourceStatus
J355 Not reported 345 810 Gas Withdrawn
J500 Not reported 345 500 Wind Operational
R52 Not reported 345 500 Wind Withdrawn
J364 Not reported 345 464 Gas Withdrawn
J499 Not reported 345 340 Wind Operational
E0002 Orient Energy Center 345 265 Gas Active
J3047 Not reported 345 263 Gas Active
J3553 Not reported n/r 263 Gas Withdrawn
S1111 Surplus; J500 n/r 263 Hybrid Active
J527 Not reported 345 250 Wind Operational
J528 Not reported 345 200 Wind Withdrawn
R38 Not reported 345 200 Wind Operational
R53 Not reported 161 200 Wind Withdrawn
R41 Not reported 345 100 Wind Operational
J3554 Not reported n/r 96 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.