MISO request J499

MISO queue ID J499

Queue request J499 was listed in the MISO interconnection queue at the end of 2025 as a 340 MW wind project in Adair County, IA, according to Berkeley Lab’s queue data file. The filing names MEC Fallow-Grimes line (18 miles east of Fallow substation) as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of March 1, 2016.

Queue IDJ499
Project nameNot reported
Status (as published)Operational
SubstationMEC Fallow-Grimes line (18 miles east of Fallow substation)
Point of interconnectionMEC 345 kV Fallow-Grimes line (18 miles east of Fallow substation)
CountyAdair
StateIA
Voltage345 kV
Capacity340 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2016-03-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Adair, IA: 15 requests in the MISO queue, 8 active totaling 2,181 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2016-FEB West
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)GIA
Queue date2015-11-13
Interconnection agreement date2019-02-08
Operational date2016-03-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.