Surplus; J500 (S1111) was listed in the MISO interconnection queue at the end of 2025 as a 263 MW hybrid project in Adair County, IA, according to Berkeley Lab’s queue data file. The filing names ORIENT as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 1, 2027.

Queue IDS1111
Project nameSurplus; J500
Status (as published)Active
SubstationORIENT
Point of interconnectionORIENT
CountyAdair
StateIA
VoltageNot reported
Capacity263 MW
Resource (as published)Gas+Other
Resource categoryHybrid (normalized for filtering)
Proposed online date2027-09-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Adair, IA: 15 requests in the MISO queue, 8 active totaling 2,181 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityMIDAMERICAN ENERGY CO.
Project typeGeneration
Queue date2025-07-31
Components (hybrid)Gas 263 MW + Other

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first