Tres Rios Ranch Solar

ERCOT queue ID 24INR0404

Tres Rios Ranch Solar (24INR0404) is listed in the ERCOT interconnection queue as a 508 MW solar project in Upton County, TX. The filing names Twelvemile as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, IA”, with a target commercial operation date of December 31, 2027. It records the screening study as complete on November 1, 2022 and the interconnection agreement as signed on December 30, 2025.

Queue ID24INR0404
Project nameTres Rios Ranch Solar
Status (as published)SS Completed, FIS Started, IA
SubstationTwelvemile
Point of interconnection76008 Twelvemile 345kV
CountyUpton
StateTX
Voltage345 kV
Capacity508 MW
Resource (as published)SOL/PV
Resource categorySolar (normalized for filtering)
Target commercial operation2027-12-31
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Twelvemile substation: 2 requests in the ERCOT queue, 2 active totaling 798 MW.

Queue IDProjectMWResourceStatus
25INR0451Tres Rios Ranch BESS290BatterySS Completed, FIS Started, IA

Upton, TX: 22 requests in the ERCOT queue, 18 active totaling 5,611.9 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityLectricWind LLC
CDR reporting zoneWEST
Fuel codeSOL
Technology codePV
Interconnection agreement signed2025-12-30
Screening study complete2022-11-01
Water availabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.