TNSTAGHORN1 substation interconnection queue
2 active projects totaling 180 MW in the ERCOT queue.
2 ERCOT queue filings name TNSTAGHORN1 as the point of interconnection, all in Ward County, TX.
Target commercial operation dates as filed run from Nov 2028 to Nov 2029 (2 filings). 2 active filings target a date after November 27, 2026.
Interconnecting entity as filed: Thornton Ranch Solar, LLC (2 filings).
2active projects
180active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| 25INR0606 | Proteus Thornton Ranch Solar SLF | 138 | 180 | Solar | SS Completed, FIS Started, No IA | Nov 2028 |
| 25INR0607 | Proteus Thornton Ranch Storage SLF | 138 | 0 | Battery | SS Completed, FIS Started, No IA | Nov 2029 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.
Other ERCOT queue substations in Ward County, TX
- Tap Wolf Switch - Quarry Field Switch Ckt 2: 2 active, 880 MW of 2 filed
- Tap Coyanosa - Blair Lake Sub: 2 active, 605.3 MW of 2 filed