Substation Scout

Nockenut Springs Storage 1

ERCOT queue ID 29INR0318

Queue ID29INR0318
Project nameNockenut Springs Storage 1
Status (as published)SS Completed, FIS Started, No IA
SubstationTap the Elm Creek (#) - Shaula (#) Line, CPS
Point of interconnectionTap the 345 kV Elm Creek (#5133) - Shaula (#5380) Line, CPS
CountyWilson
StateTX
Voltage345 kV
Capacity209.4 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2029-06-05
Source datasetlarge

Additional filed fields

Interconnecting EntityPecan Springs Energy, LLC
Cdr ZoneSOUTH
Fuel CodeOTH
Technology CodeBA
Screening Study Complete46211