Tap ROSSVILLESB8 () to OAKSSW8 () substation interconnection queue

2 active projects totalling 101.1 MW in the ERCOT queue.

2active projects
101.1active MW
2total filed
Queue IDProjectkVMWResourceStatus
28INR0208 Strawberry Dunes Solar SLF 138 101.1 Solar SS Completed, FIS Started, No IA
28INR0209 Strawberry Dunes BESS SLF 138 0 Battery SS Completed, FIS Started, No IA

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.