Substation Scout

TAP (#) Fowlerton - (#) SAN MIGUEL LINE Ckt-2 substation interconnection queue

3 active projects totalling 521.3 MW in the ERCOT queue.

3active projects
521.3active MW
3total filed
Queue IDProjectkVMWResourceStatus
28INR0343 Amphion Solar Phase 2 345 205.9 Solar SS Completed, FIS Started, No IA
29INR0214 Amphion Storage 345 200 Battery SS Completed, FIS Started, No IA
28INR0344 Amphion Solar Phase 3 345 115.4 Solar SS Completed, FIS Started, No IA

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.