Tap Ranger Camp - Prong Moss CKT #01 and #02 substation interconnection queue

3 active projects totaling 2,890.5 MW in the ERCOT queue.

3 ERCOT queue filings name Tap Ranger Camp - Prong Moss CKT #01 and #02 as the point of interconnection, all in Mitchell County, TX.

Target commercial operation dates as filed run from May 2027 to Apr 2029 (3 filings). 3 active filings target a date after November 27, 2026.

Interconnecting entity as filed: Mitchell BESS (1 filing), Zeus Mitchell BESS II, LLC (1 filing), Mitchell Solar, LLC (1 filing).

3active projects
2,890.5active MW
3total filed
Queue IDProjectkVMWResourceStatusTarget COD
25INR0589 Zeus Mitchell BESS 345 1,042.9 Battery SS Completed, FIS Started, No IA Apr 2029
26INR0686 Zeus Mitchell BESS II 345 1,042.9 Battery SS Completed, FIS Started, No IA May 2027
25INR0588 Zeus Mitchell Solar 345 804.7 Solar SS Completed, FIS Started, No IA Apr 2029

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.

Other ERCOT queue substations in Mitchell County, TX

All 19 ERCOT queue filings in Mitchell County, TX.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first