Zeus Mitchell Solar

ERCOT queue ID 25INR0588

Queue ID25INR0588
Project nameZeus Mitchell Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Ranger Camp - Prong Moss CKT #01 and #02
Point of interconnectionTap 345 kV 10049 Ranger Camp - 10057 Prong Moss CKT #01 and #02
CountyMitchell
StateTX
Voltage345 kV
Capacity804.7 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2029-04-17
Source datasetlarge

Additional filed fields

Interconnecting EntityMitchell Solar, LLC
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Screening Study Complete45462
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.