Tap Cisco - MTNBRANCH_8 substation interconnection queue
2 active projects totalling 459 MW in the ERCOT queue.
2active projects
459active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 26INR0603 | Damia Solar | 138 | 306 | Solar | SS Completed, FIS Started, No IA |
| 26INR0602 | Damia Storage | 138 | 153 | Battery | SS Completed, FIS Started, No IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.