Substation Scout

Eastland, TX interconnection queue

12 active projects totalling 1,353 MW in the ERCOT queue.

12active projects
1,353active MW
12total filed
Queue IDProjectkVMWResourceStatus
26INR0603 Damia Solar 138 306 Solar SS Completed, FIS Started, No IA
29INR0274 Richardson McClung Ranch Solar 138 252 Solar SS Completed, FIS Started, No IA
29INR0275 Richardson McClung Ranch BESS 138 205.5 Battery SS Completed, FIS Started, No IA
26INR0468 Basketflower Solar 138 183 Solar SS Completed, FIS Completed, No IA
26INR0602 Damia Storage 138 153 Battery SS Completed, FIS Started, No IA
28INR0195 Star Grass Renewable Energy Solar SLF 138 150 Solar SS Completed, FIS Started, No IA
26INR0467 Basketflower Storage 138 92 Battery SS Completed, FIS Completed, No IA
21INR0546 Anchor Wind III 345 16 Wind SS Completed, FIS Completed, IA
26INR0726 Roadrunner Crossing Wind (Uprate) 345 2.7 Wind SS Completed, FIS Completed, No IA
23INR0538 Roadrunner Crossing BESS SLF 354 0 Battery SS Completed, FIS Completed, IA
28INR0197 Star Grass Renewable Energy Storage SLF 138 0 Battery SS Completed, FIS Started, No IA
18INR0064 Silver Star repower 138 -7.2 Wind SS Completed, FIS Completed, IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.