Tap CENIZO7C - DELSOL7C (New ETT Tiempo Substation) substation interconnection queue
2 active projects totaling 391.5 MW in the ERCOT queue.
2 ERCOT queue filings name Tap CENIZO7C - DELSOL7C (New ETT Tiempo Substation) as the point of interconnection, all in Zapata County, TX.
Target commercial operation date as filed: Dec 2027 (2 filings). 2 active filings target a date after November 27, 2026.
Interconnecting entity as filed: Vaquero Wind Energy, LLC (2 filings).
2active projects
391.5active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| 24INR0505 | Corralitos Wind 1 | 345 | 196.1 | Wind | SS Completed, FIS Started, IA | Dec 2027 |
| 24INR0506 | Corralitos Wind 2 | 345 | 195.4 | Wind | SS Completed, FIS Started, IA | Dec 2027 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.
Other ERCOT queue substations in Zapata County, TX
- # Rapido: 2 active, 395.6 MW of 2 filed
- ETT Tiempo # Substation (Tap on CENIZO7C - DELSOL7C): 2 active, 391.5 MW of 2 filed
- Revilla: 2 active, 203.6 MW of 2 filed
- tap Zapata - Lopeno4A: 2 active, 155.7 MW of 2 filed