Substation Scout

Del Sol substation interconnection queue

2 active projects totalling 405.4 MW in the ERCOT queue.

2active projects
405.4active MW
2total filed
Queue IDProjectkVMWResourceStatus
20INR0162 Diamondback solar 345 203.8 Solar SS Completed, FIS Completed, IA
16INR0081 Mesteno Wind 345 201.6 Wind SS Completed, FIS Completed, IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.