Del Sol
Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Starr County, plus 1 on its Cancelled tab. First named in the release with data as of February 1, 2015.
A HIFLD substation record has the same name and county: DEL SOL (STARR County). The names agree; that does not confirm they are the same facility.
Generation interconnection requests filed in Starr, TX: ERCOT queue, 21 active of 23. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Del Sol to Frontera: Build New 345 kV Double Circuit Line Build new 345 kV double circuit line from Del Sol to Frontera. Expand Frontera Station and install two (2) autotransformers. ERCOT project 66101 · utility no. TP2020838 · RPG 21RPG017 |
AEP TCC/ETT Tier 1 |
Planned Current-year planned tab |
345 | Oct 2026 | Del Sol to Frontera Starr / Hidalgo County |
Del Sol, Frontera |
| Cruce to Del Sol: Construct New 345 kV Double Circuit Line Construct a new 345 kV double circuit line from Cruce to Del Sol ERCOT project 67324 · utility no. TP2022032 · RPG 21RPG017 |
AEP TCC/ETT Tier 1 |
Under Construction Current-year planned tab |
345 | Nov 2026 | Cruce to Del Sol Jim Hogg / Starr County |
Cruce, Del Sol |
| Del Sol: Construct New 345 kV Terminal Interconnect Diamondback Solar to the Del Sol 345 kV station ERCOT project 90040 · utility no. TP2024116 |
ETT Tier 4 |
Planned Future tab |
345 | Sep 2027 | Del Sol Starr County |
Del Sol |
On the Cancelled tab
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Equinox Solar Project ERCOT project 69469 |
AEP TCC Tier 4 |
Not reported Cancelled tab |
345 | Jun 2025 | Cenizo to Del Sol Starr County |
Cenizo, Del Sol |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 66101 | Projected in-service date | Sep 2026 → Oct 2026 |
| February 1, 2026 | 66101 | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 67324 | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 90040 | Projected in-service date | Jun 2027 → Sep 2027 |
| October 1, 2025 | 67324 | Status as reported | Planned → Under Construction |
| October 1, 2025 | 69469 | Projected in-service date | Jan 2025 → Jun 2025 |
| February 1, 2025 | 66101 | Projected in-service date | May 2026 → Sep 2026 |
| February 1, 2025 | 69469 | Projected in-service date | Aug 2024 → Jan 2025 |
| February 1, 2025 | 90040 | First listed | on the Future tab |
| October 1, 2024 | 69469 | Moved between tabs | Future → Cancelled |
| October 1, 2024 | 69469 | Projected in-service date | Nov 2026 → Aug 2024 |
| June 1, 2024 | 69469 | Projected in-service date | Nov 2025 → Nov 2026 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.