3 active projects totalling 236.7 MW in the ERCOT queue.

3active projects
236.7active MW
3total filed
Queue IDProjectkVMWResourceStatus
20INR0216 Starr Solar Ranch 138 136.7 Solar SS Completed, FIS Completed, IA
23INR0354 Bordertown BESS 138 100 Battery SS Completed, FIS Started, IA
25INR0379 Starr Storage 138 0 Battery SS Completed, FIS Started, No IA