Falcon II BESS (28INR0483) is listed in the ERCOT interconnection queue as a 103.3 MW battery project in Zapata County, TX. The filing names Revilla as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of February 16, 2032. It records the screening study as complete on June 17, 2026.
| Queue ID | 28INR0483 |
|---|---|
| Project name | Falcon II BESS |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Revilla |
| Point of interconnection | 8004 Revilla 138 kV |
| County | Zapata |
| State | TX |
| Voltage | 138 kV |
| Capacity | 103.3 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2032-02-16 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Revilla substation: 2 requests in the ERCOT queue, 2 active totaling 203.6 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 28INR0482 | Falcon II Solar | 100.3 | Solar | SS Completed, FIS Started, No IA |
Zapata, TX: 28 requests in the ERCOT queue, 27 active totaling 6,291.1 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Falcon Energy Project |
|---|---|
| CDR reporting zone | SOUTH |
| Fuel code | OTH |
| Technology code | BA |
| Screening study complete | 2026-06-17 |