Prairie Branch Solar

ERCOT queue ID 28INR0422

Queue ID28INR0422
Project namePrairie Branch Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationTap # Krum West - # Riley Ckt 1
Point of interconnectionTap 345kV #1730 Krum West - #6111 Riley Ckt 1
CountyMontague
StateTX
Voltage345 kV
Capacity301.2 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2029-12-01
Source datasetlarge

Additional filed fields

Interconnecting EntityPrairie Branch Energy, LLC
Cdr ZoneNORTH
Fuel CodeSOL
Technology CodePV
Screening Study Complete45975
Air PermitNot Required
Water AvailabilityNot Required