Substation Scout

Tap # Krum West - # Riley Ckt 1 substation interconnection queue

2 active projects totalling 611.4 MW in the ERCOT queue.

2active projects
611.4active MW
2total filed
Queue IDProjectkVMWResourceStatus
28INR0423 Prairie Branch BESS 345 310.2 Battery SS Completed, FIS Started, No IA
28INR0422 Prairie Branch Solar 345 301.2 Solar SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.