Substation Scout

2 Cedar Wind

ERCOT queue ID 28INR0286

Queue ID28INR0286
Project name2 Cedar Wind
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Valley South – Anna Switch
Point of interconnectionTap 345kV 1729 Valley South – Anna Switch 2373
CountyFannin
StateTX
Voltage345 kV
Capacity180 MW
Resource (as published)WIN/WT
Resource categoryWind (normalised for filtering)
Target commercial operation2028-05-02
Source datasetlarge

Additional filed fields

Interconnecting EntitySunWR, LLC
Cdr ZoneNORTH
Fuel CodeWIN
Technology CodeWT
Screening Study Complete45930
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.