Fannin, TX interconnection queue
3 active projects totalling 1,362.7 MW in the ERCOT queue.
3active projects
1,362.7active MW
3total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 29INR0191 | Black Mountain Fannin Gas | 345 | 990.6 | Gas | SS Started, FIS Started, No IA |
| 27INR0145 | Steelhead Energy Storage | 138 | 192.1 | Battery | SS Completed, FIS Started, No IA |
| 28INR0286 | 2 Cedar Wind | 345 | 180 | Wind | SS Completed, FIS Started, No IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.