Substation Scout

Fannin, TX interconnection queue

3 active projects totalling 1,362.7 MW in the ERCOT queue.

3active projects
1,362.7active MW
3total filed
Queue IDProjectkVMWResourceStatus
29INR0191 Black Mountain Fannin Gas 345 990.6 Gas SS Started, FIS Started, No IA
27INR0145 Steelhead Energy Storage 138 192.1 Battery SS Completed, FIS Started, No IA
28INR0286 2 Cedar Wind 345 180 Wind SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.