Substation Scout

Sayle Solar SLF

ERCOT queue ID 27INR0251

Queue ID27INR0251
Project nameSayle Solar SLF
Status (as published)SS Completed, FIS Started, No IA
SubstationTap # Edna - # El Toro SW
Point of interconnectionTap 69kV #5522 Edna - #5518 El Toro SW
CountyJackson
StateTX
Voltage69 kV
Capacity122.4 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-05-31
Source datasetlarge

Additional filed fields

Interconnecting EntitySayle Solar LLC
Cdr ZoneSOUTH
Fuel CodeSOL
Technology CodePV
Screening Study Complete45534
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.