Substation Scout

Honey Mesquite Wind Farm

ERCOT queue ID 26INR0447

Queue ID26INR0447
Project nameHoney Mesquite Wind Farm
Status (as published)SS Completed, FIS Completed, IA
SubstationSand Bluff
Point of interconnection59902 Sand Bluff 345kV
CountyGlasscock
StateTX
Voltage345 kV
Capacity174 MW
Resource (as published)WIN/WT
Resource categoryWind (normalised for filtering)
Target commercial operation2026-12-31
Source datasetlarge

Additional filed fields

Interconnecting EntityHoney Mesquite Wind Farm , LLC
Cdr ZoneWEST
Fuel CodeWIN
Technology CodeWT
Ia Signed45545
Screening Study Complete45462
Fis Approved45911
Air PermitNot Required
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.