Sterling, TX interconnection queue
7 active projects totalling 1,288.3 MW in the ERCOT queue.
7active projects
1,288.3active MW
7total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 27INR0367 | Goat Mountain Wind-Repower | 345 | 303.2 | Wind | SS Completed, FIS Completed, IA |
| 27INR0076 | Bob Creek Wind | 345 | 239.5 | Wind | SS Completed, FIS Started, IA |
| 29INR0185 | Roan Solar Phase 1 | 345 | 205.9 | Solar | SS Completed, FIS Started, No IA |
| 29INR0187 | Roan Solar Phase 2 | 345 | 205.9 | Solar | SS Completed, FIS Started, No IA |
| 26INR0589 | Goat Mountain BESS | 345 | 201.1 | Battery | SS Completed, FIS Started, No IA |
| 26INR0611 | Goat Mountain BESS 2 | 345 | 100.7 | Battery | SS Completed, FIS Started, No IA |
| 17INR0054 | Capricorn I & III repower | 138 | 32 | Wind | SS Completed, FIS Completed, IA |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.