Timber Cove Storage SLF

ERCOT queue ID 26INR0394

Queue ID26INR0394
Project nameTimber Cove Storage SLF
Status (as published)SS Completed, FIS Started, No IA
SubstationTap 212 Winkler - Pin Oak
Point of interconnectionTap 138 kV 212 Winkler - 3510 Pin Oak
CountyFreestone
StateTX
Voltage138 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2027-06-01
Source datasetlarge

Additional filed fields

Interconnecting EntityFreestone Solar, LLC
Cdr ZoneNORTH
Fuel CodeOTH
Technology CodeBA
Screening Study Complete45390

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.