Substation Scout

Zeus Spade BESS

ERCOT queue ID 26INR0387

Zeus Spade BESS (26INR0387) is listed in the ERCOT interconnection queue as a 446.3 MW battery project in Mitchell County, TX. The filing names Tap Morgan Creek to Gasconades Creek as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of March 20, 2028. It records the screening study as complete on June 25, 2024.

Queue ID26INR0387
Project nameZeus Spade BESS
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Morgan Creek to Gasconades Creek
Point of interconnectionTap 345 kV 1030 Morgan Creek to 76030 Gasconades Creek
CountyMitchell
StateTX
Voltage345 kV
Capacity446.3 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2028-03-20
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Tap Morgan Creek to Gasconades Creek substation: 2 requests in the ERCOT queue, 2 active totaling 1,433.6 MW.

Queue IDProjectMWResourceStatus
26INR0386Zeus Spade Wind987.3WindSS Completed, FIS Started, No IA

Mitchell, TX: 19 requests in the ERCOT queue, 17 active totaling 7,498.1 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entitySpade BESS
CDR reporting zoneWEST
Fuel codeOTH
Technology codeBA
Screening study complete2024-06-25

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first