Substation Scout

Zeus Spade BESS

ERCOT queue ID 26INR0387

Queue ID26INR0387
Project nameZeus Spade BESS
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Morgan Creek to Gasconades Creek
Point of interconnectionTap 345 kV 1030 Morgan Creek to 76030 Gasconades Creek
CountyMitchell
StateTX
Voltage345 kV
Capacity446.3 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2028-03-20
Source datasetlarge

Additional filed fields

Interconnecting EntitySpade BESS
Cdr ZoneWEST
Fuel CodeOTH
Technology CodeBA
Screening Study Complete45468

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.