Zeus Spade Wind

ERCOT queue ID 26INR0386

Queue ID26INR0386
Project nameZeus Spade Wind
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Morgan Creek to Gasconades Creek
Point of interconnectionTap 345 kV 1030 Morgan Creek to 76030 Gasconades Creek
CountyMitchell
StateTX
Voltage345 kV
Capacity987.3 MW
Resource (as published)WIN/WT
Resource categoryWind (normalised for filtering)
Target commercial operation2027-03-20
Source datasetlarge

Additional filed fields

Interconnecting EntitySpade Wind, LLC
Cdr ZoneWEST
Fuel CodeWIN
Technology CodeWT
Screening Study Complete45468
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.