Oyster Creek Storage I SLF
ERCOT queue ID 26INR0118
Oyster Creek Storage I SLF (26INR0118) is listed in the ERCOT interconnection queue as a battery request filed at 0 MW (a net change or energy-only filing) in Brazoria County, TX. The filing names Tap Angleton - Clute as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of April 1, 2029. It records the screening study as complete on September 22, 2023.
| Queue ID | 26INR0118 |
|---|---|
| Project name | Oyster Creek Storage I SLF |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Tap Angleton - Clute |
| Point of interconnection | Tap 138kV 42110 Angleton - 42050 Clute |
| County | Brazoria |
| State | TX |
| Voltage | 138 kV |
| Capacity | 0 MW (0 MW as filed — net change or energy-only) |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2029-04-01 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Tap Angleton - Clute substation: 2 requests in the ERCOT queue, 2 active totaling 0 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 26INR0117 | Oyster Creek Solar I SLF | 0 | Solar | SS Completed, FIS Started, No IA |
Brazoria, TX: 63 requests in the ERCOT queue, 54 active totaling 10,984.8 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Oyster Creek Solar 1, LLC |
|---|---|
| CDR reporting zone | COASTAL |
| Fuel code | OTH |
| Technology code | BA |
| Screening study complete | 2023-09-22 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.