Yellow Cat Wind
ERCOT queue ID 25INR0018
Yellow Cat Wind (25INR0018) is listed in the ERCOT interconnection queue as a 262 MW wind project in Navarro County, TX. The filing names Tap Venus - Navarro as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of March 26, 2027. It records the screening study as complete on November 5, 2021, the full interconnection study as approved on December 9, 2025 and the interconnection agreement as signed on July 9, 2024.
| Queue ID | 25INR0018 |
|---|---|
| Project name | Yellow Cat Wind |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | Tap Venus - Navarro |
| Point of interconnection | Tap 345kV 1906 Venus - 68091 Navarro |
| County | Navarro |
| State | TX |
| Voltage | 345 kV |
| Capacity | 262 MW |
| Resource (as published) | WIN/WT |
| Resource category | Wind (normalized for filtering) |
| Target commercial operation | 2027-03-26 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Tap Venus - Navarro substation: 2 requests in the ERCOT queue, 2 active totaling 663.6 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 29INR0196 | Two Step Solar | 401.6 | Solar | SS Completed, FIS Started, No IA |
Navarro, TX: 29 requests in the ERCOT queue, 26 active totaling 4,412.7 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Yellow Cat Wind LLC |
|---|---|
| CDR reporting zone | NORTH |
| Fuel code | WIN |
| Technology code | WT |
| Interconnection agreement signed | 2024-07-09 |
| Screening study complete | 2021-11-05 |
| Full interconnection study approved | 2025-12-09 |
| Air permit | Not Required |
| Water availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.