Substation Scout

Big Star Storage

ERCOT queue ID 21INR0469

Big Star Storage (21INR0469) is listed in the ERCOT interconnection queue as a 80 MW battery project in Bastrop County, TX. The filing names Tap Lytton - Holman as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Completed, IA”, with a target commercial operation date of September 25, 2026. It records the screening study as complete on March 26, 2020, the full interconnection study as approved on July 19, 2021 and the interconnection agreement as signed on October 2, 2020.

Queue ID21INR0469
Project nameBig Star Storage
Status (as published)SS Completed, FIS Completed, IA
SubstationTap Lytton - Holman
Point of interconnectionTap 345kV 9074 Lytton - 9073 Holman
CountyBastrop
StateTX
Voltage345 kV
Capacity80 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalized for filtering)
Target commercial operation2026-09-25
Source datasetlarge

In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.

Same substation and county

Tap Lytton - Holman substation: 2 requests in the ERCOT queue, 2 active totaling 283.1 MW.

Queue IDProjectMWResourceStatus
21INR0413Big Star Solar203.1SolarSS Completed, FIS Completed, IA

Bastrop, TX: 16 requests in the ERCOT queue, 14 active totaling 5,098.7 MW.

Tracked changes

No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →

Additional filed fields

Interconnecting entityRWE Solar Development, LLC
CDR reporting zoneSOUTH
Fuel codeOTH
Technology codeBA
Interconnection agreement signed2020-10-02
Screening study complete2020-03-26
Full interconnection study approved2021-07-19

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first