Mountaineer Solar
ERCOT queue ID 21INR0294
| Queue ID | 21INR0294 |
|---|---|
| Project name | Mountaineer Solar |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Brown |
| Point of interconnection | 1444 Brown 345 kV |
| County | Brown |
| State | TX |
| Voltage | 345 kV |
| Capacity | 329.3 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2029-09-01 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Mustang Mountaineer Solar LLC |
|---|---|
| Cdr Zone | NORTH |
| Fuel Code | SOL |
| Technology Code | PV |
| Screening Study Complete | 43627 |
| Air Permit | Not Required |
| Water Availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.