Tom Green, TX interconnection queue
11 active projects totalling 2,407.5 MW in the ERCOT queue.
11active projects
2,407.5active MW
11total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 29INR0328 | Moon Chapel Solar | 345 | 402 | Solar | SS Completed, FIS Started, No IA |
| 27INR0445 | Moon Chapel Wind | 345 | 379.2 | Wind | SS Completed, FIS Started, No IA |
| 25INR0339 | Fort Concho Energy storage | 138 | 251.2 | Battery | SS Completed, FIS Started, No IA |
| 25INR0853 | Tango Lily BESS | 138 | 201 | Battery | SS Completed, FIS Started, No IA |
| 29INR0231 | Tango Lily Solar | 138 | 201 | Solar | SS Completed, FIS Started, No IA |
| 23INR0312 | Hofbrau BESS | 138 | 180.7 | Battery | SS Completed, FIS Started, No IA |
| 20INR0247 | Water Valley Wind Energy | 345 | 180 | Wind | SS Completed, FIS Started, IA |
| 26INR0083 | Zeppelin Energy Storage | n/r | 163.9 | Battery | SS Completed, FIS Started, No IA |
| 26INR0454 | Dove Creek Solar | 345 | 163.6 | Solar | SS Completed, FIS Started, No IA |
| 26INR0455 | Dove Creek Storage | 345 | 162.5 | Battery | SS Completed, FIS Started, No IA |
| 23INR0224 | Morning Glory Solar | 345 | 122.4 | Solar | SS Completed, FIS Started, No IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.