Fort Concho Energy storage
ERCOT queue ID 25INR0339
| Queue ID | 25INR0339 |
|---|---|
| Project name | Fort Concho Energy storage |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Tap # Schkade - # Twin Buttes Line; LCRA |
| Point of interconnection | Tap 138 kV #76320 Schkade - #76011 Twin Buttes Line; LCRA |
| County | Tom Green |
| State | TX |
| Voltage | 138 kV |
| Capacity | 251.2 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2028-12-31 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Rocky Mountain Energy Development, LLC |
|---|---|
| Cdr Zone | WEST |
| Fuel Code | OTH |
| Technology Code | BA |
| Screening Study Complete | 45044 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.