Dove Creek Solar

ERCOT queue ID 26INR0454

Queue ID26INR0454
Project nameDove Creek Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationTap at Big Hill - Twin Buttes line ( / )
Point of interconnectionTap at Big Hill - Twin Buttes 345 kV line (76003 / 76009)
CountyTom Green
StateTX
Voltage345 kV
Capacity163.6 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-07-01
Source datasetlarge

Additional filed fields

Interconnecting EntityDove Creek Solar, LLC
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Screening Study Complete45573
Air PermitNot Required
Water AvailabilityNot Required