Substation Scout

Morning Glory Solar

ERCOT queue ID 23INR0224

Queue ID23INR0224
Project nameMorning Glory Solar
Status (as published)SS Completed, FIS Started, No IA
Substationtap Amos Creek - Twin Buttes
Point of interconnectiontap 345kV 7077 Amos Creek - 76009 Twin Buttes
CountyTom Green
StateTX
Voltage345 kV
Capacity122.4 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-11-30
Source datasetlarge

Additional filed fields

Interconnecting EntityArmadillo Solar, LLC
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Screening Study Complete44446
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.