Maverick, TX interconnection queue
8 active projects totalling 1,508.3 MW in the ERCOT queue.
8active projects
1,508.3active MW
8total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 26INR0311 | Senator Aggreko Solar | 138 | 258.9 | Solar | SS Completed, FIS Started, IA |
| 27INR0389 | Sugaree Solar | 138 | 251.4 | Solar | SS Completed, FIS Started, IA |
| 27INR0465 | Althea Storage | n/r | 251.3 | Battery | SS Completed, FIS Started, IA |
| 27INR0253 | Old Victory Energy Center | 138 | 202.5 | Battery | SS Completed, FIS Started, No IA |
| 24INR0142 | De Los Santos | 138 | 201 | Battery | SS Completed, FIS Started, No IA |
| 24INR0617 | Serrano Storage | 138 | 185.6 | Battery | SS Completed, FIS Started, No IA |
| 26INR0312 | Senator Aggreko Storage | 138 | 147.6 | Battery | SS Completed, FIS Started, IA |
| 25INR0593 | Escondido BESS | 138 | 10 | Battery | In Queue |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.