Substation Scout

Kent, TX interconnection queue

7 active projects totalling 1,629.6 MW in the ERCOT queue, plus 1 with terminal status (shown greyed).

7active projects
1,629.6active MW
8total filed
Queue IDProjectkVMWResourceStatus
29INR0294 Spurland Solar III n/r 321.9 Solar SS Started, FIS Started, No IA
24INR0398 Lake Henry Wind n/r 305 Wind Inactive
27INR0447 Jay Flat BESS 345 259.4 Battery SS Completed, FIS Started, No IA
27INR0435 Clairemont Solar 1 345 251.8 Solar SS Completed, FIS Completed, IA
29INR0394 Buzzer Butte Solar 345 242.8 Solar SS Started, FIS Started, No IA
30INR0164 Buzzer Butte 2 Solar 345 242.8 Solar SS Started, FIS Started, No IA
22INR0215 TEXAS SOLAR NOVA 3 345 200.2 Solar SS Completed, FIS Started, No IA
28INR0301 Carpet Tech Solar One 345 110.7 Solar SS Completed, FIS Started, No IA

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.