Kent, TX interconnection queue

4 active projects totalling 822.1 MW in the ERCOT queue, plus 1 with terminal status (shown greyed).

4active projects
822.1active MW
5total filed
Queue IDProjectkVMWResourceStatus
24INR0398 Lake Henry Wind n/r 305 Wind Inactive
27INR0447 Jay Flat BESS 345 259.4 Battery SS Completed, FIS Started, No IA
27INR0435 Clairemont Solar 1 345 251.8 Solar SS Completed, FIS Started, IA
22INR0215 TEXAS SOLAR NOVA 3 345 200.2 Solar SS Completed, FIS Started, No IA
28INR0301 Carpet Tech Solar One 345 110.7 Solar SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.