Kent, TX interconnection queue
7 active projects totalling 1,629.6 MW in the ERCOT queue, plus 1 with terminal status (shown greyed).
7active projects
1,629.6active MW
8total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 29INR0294 | Spurland Solar III | n/r | 321.9 | Solar | SS Started, FIS Started, No IA |
| 24INR0398 | Lake Henry Wind | n/r | 305 | Wind | Inactive |
| 27INR0447 | Jay Flat BESS | 345 | 259.4 | Battery | SS Completed, FIS Started, No IA |
| 27INR0435 | Clairemont Solar 1 | 345 | 251.8 | Solar | SS Completed, FIS Completed, IA |
| 29INR0394 | Buzzer Butte Solar | 345 | 242.8 | Solar | SS Started, FIS Started, No IA |
| 30INR0164 | Buzzer Butte 2 Solar | 345 | 242.8 | Solar | SS Started, FIS Started, No IA |
| 22INR0215 | TEXAS SOLAR NOVA 3 | 345 | 200.2 | Solar | SS Completed, FIS Started, No IA |
| 28INR0301 | Carpet Tech Solar One | 345 | 110.7 | Solar | SS Completed, FIS Started, No IA |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.