Substation Scout

TEXAS SOLAR NOVA 3

ERCOT queue ID 22INR0215

Queue ID22INR0215
Project nameTEXAS SOLAR NOVA 3
Status (as published)SS Completed, FIS Started, No IA
Substationtap Dermott - Cottonwood
Point of interconnectiontap 345kV 11305 Dermott - 59904 Cottonwood
CountyKent
StateTX
Voltage345 kV
Capacity200.2 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2026-01-31
Source datasetlarge

Additional filed fields

Interconnecting EntityTexas Solar Nova 1, LLC
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Screening Study Complete42368
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.