Substation Scout

Elan BESS

ERCOT queue ID 25INR0372

Queue ID25INR0372
Project nameElan BESS
Status (as published)SS Completed, FIS Completed, No IA
SubstationNeedville
Point of interconnection42380 Needville 138kV
CountyFort Bend
StateTX
Voltage138 kV
Capacity202.7 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2026-12-31
Source datasetlarge

Additional filed fields

Interconnecting EntityElan BESS, LLC
Cdr ZoneHOUSTON
Fuel CodeOTH
Technology CodeBA
Screening Study Complete45082
Fis Approved45372